Hi Expert,

I want to ask about Project Cost Overview on Fiori why it shows me the Blank Result

I have configured on FSV and semantic tags on it
here the sap notes that I configured

https://launchpad.support.sap.com/#/notes/2767526
https://launchpad.support.sap.com/#/notes/2636906
https://launchpad.support.sap.com/#/notes/2799100

anything wrong on it?
or is that any missed on configuration?

thanks

Kehkashan
Participant
0 Kudos

Hi,

I am sure this report is used to display cost that come from SAP BPC.This report cannot be used to display cost planned using cost element,easy cost planning or overal planning.

Kindly check the App details in Fiori Library- App Documentation.

Regards,

Kehkashan A J

0 Kudos

Hello, Yofi!

Did you find out the solution for the problem displaying the values in Project Cost Overview reports on Fiori?

I have the same problem here.

Thanks for sharing.

P.Valentina.

0 Kudos

Hi All,

thanks for the responses,

I haven't solutions on this case,

I tried to contact SAP and raised ticket, but they said this still on development, hahaha

what we tried are :
1. configure the BPC,
2. configure the SAP PS and also SAP CPM.
3. and SAP BW

Accepted Solutions (0)

Answers (4)

Answers (4)

wnash7658
Active Participant

If you have applied the OSS notes then best to send an OSS message to SAP.

former_member469721
Participant

Basically Project Cost report fiori app works based on FSV you have configured.

follow the instruction as mentioned in note https://launchpad.support.sap.com/#/notes/2799100. This helps you to resolve the issue.

Follow the steps as mentioned below:

1.Check for FSV (YPS2) and assign G/L.

2.Have FS item where you added G/L is FSV handy ( if FS item are not visible enable them going to setting)

3.Create Semantic tag newly with header semantic tag as ACT_COST

4.Assign sematic tag newly created and ACT_COST (both semantic tag needs to be assigned) to FSV considering FS item (mentioned in step 2).

Check for the report. You will be see the cost and actuals.

Regards,

Pradeep

brahms86
Active Contributor
0 Kudos

The solution to this problem is provided in SAP-Note https://launchpad.support.sap.com/#/notes/2799100

The answer depends actually on your exact S/4 version.

0 Kudos

Refer to part 2 under blog (URL below), you need to adjust variables to pull values from ACDOCP Table if you have planned the Project Cost using Fiori app : ‘Import Financial Plan Data’. Do this for the WBS query instead of IO example in the Blog.

https://blogs.sap.com/2019/10/28/overhead-planning-and-analytical-reporting-of-management-accounting...