Production version SUBC gets cleared in subcontracting Purchase Requisition when assigning contract

36 Views

Dear experts we have following issue on PR type subcontracting that is creating troubles in downward process: automatic conversion of PR to PO and automatic change of PO

PR type subcontracting have Production version field (VERID) set as "SUBC"

When PR is assigned to contract value SUBC gets cleared.

Our developers found that this issue is caused by current logic in the class CL_SOURCE_OF_SUPPLY_MM Method UPDATE. The given method set LS_SOURC_DATA-VERID as Space, but this does not make any sense to me as in a Purchasing Contract there is not a Production version field available. In past logic BOM was re-exploded. But with a later note 1874041 applied via Support Package the code lines responsible to automatically re-explode BOM have been deactivated. Any suggestion to keep "SUBC" value in subcontracting PR (apart workaround to remind users to manually re-explode BOM after assigning contract) ? Thanks