cancel
Showing results for 
Search instead for 
Did you mean: 

TCI behaviour during transporting

STM23
Explorer
0 Kudos

Hello,

During the TCI implementation in the development system, SPAM is showing a screen saying that there are Open Data extraction requests. I could process this requests in development system but how are they processed during the transport to the production system? During the transportation process to the production system, the process stops to asking to process the open data requests or only it's done in development system during the import of the tci and after that is transport smoothly to the production as other normal transport request?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

dirk_ganzke
Discoverer
0 Kudos

Hello Sergio,

all SPAM Phases are executed during the implementation of TCIs - like to an SP Import.

But there are no such checks during the import of the Transport Request into the follow-up systems.

Kind Regards,

Dirk Ganzke

STM23
Explorer
0 Kudos

Thanks Dirk for your answer.

But it would be necessary to process this open data requests previously of the transport request to the production system?

You are saying that this checks are not executed but It will necessary to process it to avoid loss in the data with the change of the structures.

Regards