Process chain

former_member251664
Participant
0 Kudos

DSO is loaded and activated in 2 different process chain, and due to object locking and overlap, we are seeing DSO activation is failing causing manual intervention to resolve the overlap.

ZXX_MATERIAL_MOVEMENTS and ZYY_MM_OTHERS

Resolve the duplication and make sure DSO activation is happening only once.

Accepted Solutions (0)

Answers (1)

Answers (1)

kohesco
Active Contributor
0 Kudos

Hi,

if you really have the need to let the two PC co-exist next to eachother, you can set the job of activation to automatically repeat. go in change mode and right click on the process and choose..repeat automatically, when the process goes in error caused by lock it will repeat himself respecting the parameters you have filled out.

Koen