on 09-16-2020 7:12 AM
Hello Team,
We are planning to upgrade ECC system, EHP6 FOR SAP ERP 6.0 - From SP11 to SP25.
Kindly suggest your opinion based on your experience what would be the Impacts in CO module /Bugs may occur. How to resolve the issues. Kindly provide me the list of activity should be taken care by CO Functional consultant.
Kindly share your feedback based on your experience, it would be great. Thanks in advance.
The functional consultant should review the side effect SAP notes provided by the updated support packs.
That said, we have upgraded CO several times without issues; we actively review the side effect notes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That's a good question
1. check side effect notes
2. We do unit testing in the DEV box, then regression testing in the R3Q box.
3. We have a pre-and post day checklist - run reports before the system is down and then check them after the support packs are applied