on 09-14-2020 11:07 PM
Hello guys.
Im going to upgrade SAP Enterprise Portal 7.4 to 7.5, im going to do it in this way: sandbox, quality, productive and development system. Productive system has a different kernel version, its going to be updated this sunday.
My question is simple, can i create the XML stack for the four systems in maintenance planner right now? i must wait for productive?
Regards
Hi Marco.
1. Yes, You can create the XML in one go for all systems. before upgrade start check the all the systems kernel & SP level are same.
2. Why you are following the upgrade sandbox, quality, productive and development systems? any reason?
Regards
Sriram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sriram.
Thanks for your answer, the reason to go in that way is just a Customer request, in case they need to make a productive adjustment, they have the development environment available for changes and not wait so long for the entire landscape to be updated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.