on 09-09-2020 4:45 PM
Hello all,
I have query regarding link of SAP HR and SAP Plant Maintenance.
In SAP HR ,they put Labour is on Leave .Now how Plant Maintenance person knows that this labour is on leave.
In Plant maintenance order how it will trigger that Labour is on Leave.
Please Guide
Thanks and Regards
Prasad
Prasad,
You could probably write some code when saving an order to check if the person is available on that date/time.
Have a look at user-exit IWO10009 (SMOD) or BADI WORKORDER_UPDATE (SE18).
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Prasad,
You should see this information in the "individual" capacity leveling transactions such as CM30 and CM24.
It can also be shown in MRS if you are using it.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.