Difference between "Consulting Days" Unit and "Days" in Capacity Planning

Hi All,

Can anyone clarify me what is the difference between using "Consulting Days" Unit and "Days" in Capacity Planning.

Regards,

Stephen

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 24, 2017 at 12:20 PM

    Hello Stephen,

    SAP Knowledge Base Articles Nr. 2246124 and Nr. 1649907 provide information as to the purpose of this unit of measure. Essentially it is used as a Full Time Equivalent to represent the amount of hours typically worked in a day, as a workaround for the fact that in Project Management a full calendar day converts to 24 hours (as opposed to e.g. 8 hours).

    Regards,
    Francesco