We have a requirement where 1 mould is used to produce a 1 SFG material. Number of mould will be limited and creates constraints on the SFG planned orders. Also One mould can be used 5 times and then scraped.
We are able to achieve the constraint based on the availability of the mould using bottom up scheduling. but is there any standard way in ppds where we can restrict the usage of the mould to 5 and at a time only one usage is possible
Also is there a standard way to plan PRT's in S4 hana PPDS?