Dear SAP PS experts,
During the copy of actual amounts into a planning version I had the following issue, please see bellow:
1 - I posted 220€ of actual costs of cost for September and after
2 - Run CJ44 for the overhead calculation based on pre-configured costing sheet. Bellow a print from report S_ALR_87013543 - Actual/Plan/Variance - Where possible to see both amounts:
3 - Run tcode CJCS to copy actual amounts into a planning version, however only the actual amounts from the cost that have been posted was copied. Overheads costs were not. Please see below:
Does anyone know how it will be also possible to copied overhead amounts to the planning version?
Many thanks in advance for the great support!
JAS