Hello I am facing a problem while closing a project
It gives the error that There is still WIP remaining for one of the WBS of the project , However i have run KKA2 as well as performed settlement using CJ88 for that WBS , but still i get this error
Can someone kindly help me out on this.
Hi Taran
Are you following all the steps mentioned in the KBA 2540294 - Error KO450 is issued when closing WBS element??
PLease follow the steps and also check there is no value left by following below step
"On the start screen, go to menu 'Results Analysis -> Display Results Analysis"
Also try to change the WBS code to TECo and see if that helps
Regards
Vinita