WBS fields status option based on levels

former_member7439
Participant
0 Kudos

Hwllo

We need to make the WBS fields optioanal based on the level of WBS .The investment program position needs to be mandatory for top level WBS and optinal for lower level WBS.How can w achieve this

regrds

Paulo_Vitoriano
Active Contributor
0 Kudos

If IM program position is mandatory at Level 1 you should not assign it at any other 2+ levels to avoid inconsistentses.

Accepted Solutions (1)

Accepted Solutions (1)

NathanGenez
Active Contributor
0 Kudos

This is standard functionality for all PS fields. No validation is required.

Answers (1)

Answers (1)

0 Kudos

Hello,

You can use Validations to achieve this. SPRO--> Project System --> Structures --> Operative Structures --> WBS --> Maintain Validations.

Regards,

Karthik