Hi SAP experts,
User requested us to edit the shift schedule and definition for particular grouping name and plant in SAP.
We have done the changes through t code OP4A.
Just want to understand what will be the impact of those changes in SAP?
Regards
Hi,
Look at SAP help statement: If you change the working times, you only have to change the shift definition, not the available capacity in all the work centers affected. The system changes the available capacity automatically. Changes to the shift sequence only serve as an aid to entering intervals in capacity, and do not affect existing available capacity.
Refer below link for details
Regards,
Sharat