In STO process, if we create PO with multiple line items( po line items may have different delivery dates) and then we create VL10D the system create multiple deliveries.

My requirement is to generate single deliver. Is there any user exit or enhancement. Is it control able at PO level or VL10D level ?

0 Kudos

looking for Snote to avoid STO delivery split ?

Accepted Solutions (0)

Answers (1)

Answers (1)

vinita_kasliwal
Active Contributor
0 Kudos

Hi

This question is asked before

Pl refer below options you could explore

OSS note: 386340 - Grouping purchase orders into one delivery using Vl10*

OSS note 46668 - FAQ: Delivery split when creating deliveries

BADI LE_SHP_GN_DLV_CREATE debug and try to play around

USER-EXIT (MV50AFZ1) in the program - SAPMV50A

Refer previousl questions and see if that helps

https://answers.sap.com/questions/3401283/batch-determination-for-stock-transport-order-in-p.html

https://answers.sap.com/questions/6845626/multiple-stos-in-1-delivery.html

Let me know if this helps.

Regards

Vinita