on 08-21-2020 1:25 AM
In STO process, if we create PO with multiple line items( po line items may have different delivery dates) and then we create VL10D the system create multiple deliveries.
My requirement is to generate single deliver. Is there any user exit or enhancement. Is it control able at PO level or VL10D level ?
Hi
This question is asked before
Pl refer below options you could explore
OSS note: 386340 - Grouping purchase orders into one delivery using Vl10*
OSS note 46668 - FAQ: Delivery split when creating deliveries
BADI LE_SHP_GN_DLV_CREATE debug and try to play around
USER-EXIT (MV50AFZ1) in the program - SAPMV50A
Refer previousl questions and see if that helps
https://answers.sap.com/questions/3401283/batch-determination-for-stock-transport-order-in-p.html
https://answers.sap.com/questions/6845626/multiple-stos-in-1-delivery.html
Let me know if this helps.
Regards
Vinita
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
25 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.