Planned Exchange Rate in Project System

314 Views

Hi Gurus,

We set exchange rate P for our planning profile for project. We use Network-Activity cost planning in projects. When a life of a project is more than one Fiscal Year, the exchange rate for planned cost at network activity level would change. For example, when we first set up an Activity in FY19 and assigned planned cost to it, it would translate from object currency(say. EUR) to controlling area currency(say. USD) by using P rate of FY19. However, when we get into FY20, the exchange rate would change to P rate of FY20 which is causing issues for our cost forecasting at USD.

Do anyone know how we can lock the P rate for the planning cost conversion from EUR to USD?

Thank you very much for help.

Regards

Sasha