Change Project to enable multiple billers

0 Kudos

Hi,

SAP by Design Q.

I'm needing help within the Project Management function to change an existing project created which is set to released to enable multiple client?

lenastodal
Product and Topic Expert
Product and Topic Expert
0 Kudos

Thank you for visiting SAP Community to get answers to your questions. I am here to help you to get the most out of it.

First of all, I recommend that you familiarize yourself with https://community.sap.com/resources/questions-and-answers (if you haven't done so already), as it provides tips for preparing questions that draw responses from our members.
Please also make sure you're using all appropriate tags, so the right experts can find your question. Overall, the more details you provide, the more likely it is that members will be able to assist you. Should you wish, you can revise your question by selecting Actions, then Edit (although once someone answers your question, you'll lose the ability to edit the question - but if that happens, you can leave more details in a comment).

Finally, if you're hoping to connect with readers, please consider adding a picture to your profile. Here's how you do it: https://www.youtube.com/watch?v=F5JdUbyjfMA&list=PLpQebylHrdh5s3gwy-h6RtymfDpoz3vDS. By personalizing your profile with a photo of you, you encourage readers to respond.

Best,

Lena (SAP Community Moderator)

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member624513
Active Participant
0 Kudos

Hi keryks,

Once a Project is set to status Started or Released, some fields become “Read-Only”, such as the project ID, project type, organizational assignments, and the Billable field including Customer information.

So you cannot enable the multiple clients once the Project is Released. The only option is to cancel the Existing project and create a New Project.

.

Also once project or project task released they will be communicated to a lot of applications and objects FIN,HCM,SRM,CRM with responsible unit so that any actuals Time recoding, expense, procurement, sales on the task would be linked with cost center. The reporting unit is directly linked to financial accounting object hence the system will not allow you to change the Reporting Unit once the project is released.


Note:- A change in the backend of your system is not an option since it would lead to inconsistencies from an accounting point of view.

.

Please go through the documents below for your refernce:-

.

Let me know if it clears the question for you, and mark it as answered or leave a comment for further queries.
.