cancel
Showing results for 
Search instead for 
Did you mean: 

MD41 with scheduling option 2 Determination of Basic Dates for Planned

0 Kudos

Hi, Guru,

When I run MD41 for a finished product (BOM contains another finished product and 2 external procurement products) with schedule option 2 (Determination of Basic Dates for Planned), it gives me a very long duration basic date and production date in planned order, when I add several hours in operation, the begin and end date of production can last years. However our whole operation is only several hours (packaging)md41-1.pngmd41-2.pngmd41-3.pngmd41-4.png.

I took a look on schedule tab, it is scheduled from past time (Jan 13 2020, we are now Aug 5 2020).md41-5.png

Could Someone tell me where is the point to check and fix? I simulate the same thing in our QA, there is no problem, for sure, the capacity is not same in QA as in Prod.When I run with schedule option 1 (Determination of Basic Dates for Planned), there is no problem either.

Thanks,

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

Thanks for reply, gentlemen,

I found the problem. Our user badly set up the pooled capacity for work center (like 0.02 H per day), no wonder it takes years to finish an order!

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please check the available working Hrs on your resource and factory calendar assigned to the resource.

Also check float defined in schedule margin key Z06.

Operation end date year is not visible in screen shot 5.

Also check the recipe for operation duration in details

Best Regards,

R.Brahmankar

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Check your floats in the routing operations (wait time, queue time, move time...).

Also, go through the following note that explains the scheduling for a routing:

152319 - Consulting: Scheduling of planned order for routing

Regards,
Caetano