I have 2 shifts defined in my wc, S1 - 6.92 hr and s2 7 hr. But my wc operation time is from 07:00:00 am to 16:00:00 pm (8.33 hrs). Also in intervals above appears with standard available capacity 'X' interval. How does it effect the scheduling/capacity planning ? Do I need to change wc operation time according to shifts? What is the impact?

shifts.png wc-operation-time.png wc-intervals.png wc-intervals.png

shifts.png (10.0 kB)
wc-intervals.png (20.8 kB)
Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Jul 30, 2020 at 03:58 PM

    Hello,

    When you assign the shift to the work center then during the order scheduling system consider the timing from shift.

    If no shift assignment then system consider the standard available capacity in your case it is 07:00:00 am to 16:00:00.

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.