on 07-30-2020 7:24 AM
Dear Experts,
I have 2 shifts defined in my wc, S1 - 6.92 hr and s2 7 hr. But my wc operation time is from 07:00:00 am to 16:00:00 pm (8.33 hrs). Also in intervals above appears with standard available capacity 'X' interval. How does it effect the scheduling/capacity planning ? Do I need to change wc operation time according to shifts? What is the impact?
shifts.png wc-operation-time.png wc-intervals.png wc-intervals.png
Hello,
When you assign the shift to the work center then during the order scheduling system consider the timing from shift.
If no shift assignment then system consider the standard available capacity in your case it is 07:00:00 am to 16:00:00.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Yes thats right if you have a valid shift assignment.
I have not yet seen any such recommendation to have the operation time/break time in sync with the intervals, shifts and breaks.
May be you can define standard capacity 24 hrs working in this case.
Best Regards,
R.Brahmankar