Skip to Content
0
Jul 30, 2020 at 03:20 PM

How to JIT Truck load build for raw materials/components in Food & beverage industry in SAP S/4 HANA

73 Views Last edit Aug 05, 2020 at 07:24 PM 3 rev

I just want to find out if any of you are familiar or have worked on similar requirement/user story at any of your previous clients in SAP S/4 HANA. Its a requirement/user story at one of the US Food & Beverage industry client. The requirement is that the critical raw material/components requirements for production down to the hour/ minute timing need to be consolidated in to Truck build based on Truck capacity and schedule by item by supplier and then POs will be generated per each truck load. This is to receive those raw material/components just in time (JIT) and consumed straight in to Production as and when needed. Currently it's somewhat custom application in the client's legacy system in Oracle. If any of you have worked on this kind of scenario at previous clients then please reach out to me. Any kind of help / ideas will be appreciated.