on 08-01-2020 10:03 AM
Hi ,
Any mechanism by which we can restrict qty in procurement by material and vendor like purchase order, scheduling agreement and others ?
Is it ok to use z table to track and update whenever a document is created ? Where should we implement this logic??
Regards,
Aditya
Where you wanted to set the limit?
Are your PO directly created and send to vendor without an approval process?
Before PO getting created and approved- Internal purchasing document(PR) created and approved, if any correction done at this level.
How is the procurement setup!
Contract-- Contract release--- PR-----PR release -------PO
or
PR -------Contract ----Contract release ----- PO-----PO release
or
PO----PO release
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
With Quality Info records, it is possible to achieve. See here If not, you can go with an enhancement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.