on 07-29-2020 12:50 PM
Dear All,
I am running the scenario of PMRP, after simulation of capacity from PMRP fiori app the siuulated plan goes into inactive verspn of PIR that is 01.
Everytime I want to run the tcode MS64, to copy the plan from Inactive to active version. Can anyone suggest me to any functiponality to run the backjgroung job of MS64 or any other method to copy thr PIR from Inactivw from Activwe version .
Thanks
Tejas Khanna
Hello
You can use transaction SM36 and create a new background job for program RM60SIMU.
Regards,
Caetano