CK40N does not consider BOM component

former_member660245
Participant
0 Kudos

Hello,

When we run CK40N with one FG material at selection step system select only one FG material and cost only that material but SFG materials not considered in spite of selecting Explode multilevel structure option in selection step.

We are using S4 Hana system.

Kindly help with this.

Thanks and Regards,

Kunal Sakpal

former_member660245
Participant

Issue is resolved.

Actually valid standard cost estimate is present for SFG materials that is why it is not considering SFG materials while running CK40N transaction.

So i have deleted standard cost estimate of SFG material with tcode-CKR1 and again run the CK40N for FG material. Now it is considering SFG materials also.

BR,

Kunal Sakpal

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor

Have a look at OSS notes 1887460 and 2525752

former_member660245
Participant
0 Kudos

Hello Lakshmipathi,

Thanks for the reply.

SFG material is neither co product nor phantom assembly.

Thanks and regrads,

Kunal Sakpal