on 07-30-2020 8:08 AM
dear experts,
when the KKF6N is run the cost estimation is done and MFBF is also done without any issue, but when we tried for collective PCC through KKF6M cost estimation did not take place and which is resulting in MFBF "error determining cost estimate".
i need some experts suggestion on the same on priority.
thanks in advance
VIJAY TEJESH