Hello all sifu in SAP

i have 1 question, i want to perform PGI in DO but got error message said this

"Budget was exceeded by 6,740.00 MYR in document item 002 WBS element P-204146"

we have increased the budget, but that error still not resolve, can anyone help me?

Thank You So Much

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos
we have increased the budget

Did you increase the budge for that WBS element ? Also, please share more information on what you were trying to do and what is the Business requirement

0 Kudos

yes , we have increased the budget for that WBS element, then we also do the supplement budget, but still got an error when we perform the PGI