We have some finished materials that we are using strategy 52 to forecast and purchase the raw materials before sales orders are received.

We are trying to limit sales to our forecast both with quantity and date of production, but only when we have the order in hand.

is there a way to make make the convertible planned orders that are created once a sales order is received match the PIR (VSE)'s planned order (type VP)

example

item 1 has forecast of 10 on 10/5/20, sales order comes in with request date 9/15/20 for 5. I would like the planned order the MRP creates to still have the 10/5/20 date.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jul 23, 2020 at 02:44 AM

    Hi Chris,
    Based on my understanding about the above query.
    In case of the Planning Strategy 52, once you receive the Sales Order, during the MRP Run, System will look for the existing VP Planned Orders, in that period, if exists, system will convert that VP Planned Order, to the Convertible Planned Order, to the Quantity equal to the Sales Order Quantity.
    If you don't have any VP Panned Order in that period( available for MRP), System will create fresh convertible Planned Order, with quantity equal to the Sales Order Quantity.& will not touch the existing VP Planned Orders, which are with the future period.

    Hope, it is clear. If still any questions, please let me know.
    Thanks & Regards : Raja
    Below is one such example, as mentioned




    drrvs.png (54.1 kB)
    Add a comment
    10|10000 characters needed characters exceeded

    • Hello Raja,

      I appreciate you responses and, I understand what you're saying about trying to about trying to start final production without waiting, let me explain a little deeper

      we have products that have, high cost, long leadtime >120 days but short useful life (seasonal goods), as well as large physical size of the finished item, but small raw materials, so we have to use strategy 52 and VSE(VP planned orders) to allow us to order the raw materials. So as the sales orders come in we won't have the raw materials until the PIR date (planned order date), which is why I'd love the convertible planned order to retain the VP planned order date.

      We are also trying to limit the quantity that can be sold to the PIR quantity, for the same leadtime/useful life of the products.

      is there a way for once all PIRs are consumed to not create new planned orders?

      Thank you for your help.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.