on 07-23-2020 5:28 AM
Hi
I would like to know is it possible to relate the sequence number given in Production order along with the VIN [serial number assigned to Production order]
1.Is it possible to make VIN@Serial number assigned in production order in adherence to FIFO logic so that Production person will be upfront intimated on the VIN that is allocated to the Production order header level to avoid FIFO logic.
2.In case when CM31 or CM25 is used to change the capacity at workcentre can this be used to validate the sequence number in relation ship with VIN@Serial number mapped to Production order.
Thank you.
Vignesh V
Hello,
What is VIN Serial number ?
Do you have a Sequence Number for production order?
Please elaborate the business requirement.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi rupesh.brahmankar3
Serial number is considered as VIN - Vehicle Identification Number.
Production order - user will map the VIN under serial number tab.
We are assigning the sequence number for the Production order in assignment tab.In case user is wishing to change the sequence number of the production order based on some changes in Production due to some reason in this situation can system handle ---> Production sequence + serial number + scheduling when user is trying to handle the scheduling at work centre level as sequence number is mapped at Production order level only.
Below is illustration of the above process shown.
Vignesh V
Hello,
You can use the sequence number in order scheduling.
You have to define a sort key with field 'Sequence number' (CAUFVD-CY_SEQNR or AFVGD-CY_SEQNRV), and in dispatching production orders in transaction CM25, they can be sorted as per sequence number.
Please refer SAP KBA on it,
2670858 - Custom Field in CYUSER is not considered in Dispatch Sequence in T-code CM25
2523406 - How to Configure Dispatch Sequence in Capacity Leveling
User is wishing to change the sequence number of the production order based on some changes in Production
For that you need some kind of enhancement to update sequence number in production order base on your own logic.
Best Regards,
R.Brahmankar