Wave template determination

0 Kudos

Hi All,

How the wave template determination will happen in the below case,

Wave template is determined having the wave completion time, lets say-18:00, planned completion time of warehouse request item is 17:00 and the outbound delivery is created on the same day. In this case we cannot change the date to (-1) as the ODO is created on the same day and we do not have any other wave template determined using the condition technique.

Thanks in advance !

Accepted Solutions (1)

Accepted Solutions (1)

Ajit_Routray
Active Contributor
0 Kudos

Himohit09

I feel you need to create a new Wave Template for same day delivery.

Process in Standard:

-> Create new Delivery Priority as same day, assign into ECC Delivery/Order

-> Create new WPT-warehouse process type as same day, then determine based on delivery priority

-> Create/modify Condition table for Wave Template for same day and include WPT

-> Maintain condition for wave template determination.

Please let us know if you any doubts.

Kind Regards,

Ajit