Hi All,

The Transfer to CO only appears to be working for methods updating using FPCA (or Plan Cost). The methods which use key figures for ETC or EAC are simply not updating ECP but there are no error messages.

When we are running the Mass Forecast program /CPD/PFP_MASS_FORCAST_TRANSFER:A message appears stating the Transfer process initiated.

On checking the SLG1 log

Transfer process initiated
0TRANS_WBS_EAC_FORECAST: WBS XXXXXXX EAC transferred
Transfer process completed.

But when we check ECP values in CJ20N we get no values have flowed in. Neither there is data in the Infocube.

Regards,

Suman Misra

Add a comment
10|10000 characters needed characters exceeded

Related questions

0 Answers

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.