Skip to Content
0
Jul 21, 2020 at 02:13 PM

Predictive Material and Resource Planning in SAP S/4HANA (pMRP)

532 Views

Hi all.

Need some help with execution of Predictive Material and Resource Planning in SAP S/4HANA (1909). When i schedule pMRP simulation for my product, there is no capacity requirments are created/calculated.

All master data is exist. Simulative Long Term Planning with the same master data is working and creating capacity requirments for my resource.

Below is a result of processing scheduled pMRP simulation. There is no feasible load for producing simulated product.

Thanks for answers.

Attachments

pmrp.png (90.4 kB)