on 07-15-2020 5:17 PM
Hi,
This question is about production integration in EWM 1909. we have the items setup as cross order parts. When the production order is released, I am expecting the PMR to generate automatically but it does not. When I click on material staging (pull list) in Co01 or CO02 and save, PMR is created. Is there a setting to make it work without having to click on material staging? I tried with the prod scheduling profile setting WM request=X but it does not work.
Your help is appreciated.
Regards,
Harish
Dear hshegde,
i got the following information from Mr Pitz and it worked (see thread https://answers.sap.com/questions/13118220/sap-ewm-pmr.html)
<<<
All I got is a production scheduling profile with "WM Request" set to 2 - "Transfer Reqmt, Transfer Order, and Delivery Upon Rel" (where the last part is the important piece).
>>>
Set your WM Request to 2 in the corresponding "production scheduling profile" (material master).
P.S. Sorry for inverting some letters in your name in my first post.
Brgds
Robert Gompper
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.