Hi,

This question is about production integration in EWM 1909. we have the items setup as cross order parts. When the production order is released, I am expecting the PMR to generate automatically but it does not. When I click on material staging (pull list) in Co01 or CO02 and save, PMR is created. Is there a setting to make it work without having to click on material staging? I tried with the prod scheduling profile setting WM request=X but it does not work.

Your help is appreciated.

Regards,

Harish

RoGo
Explorer
0 Kudos

Dear Mr Hedge,

i want to inform you, that i am discussion the same topic within thread https://answers.sap.com/questions/13118220/sap-ewm-pmr.html.

Maybe this will help us both.

Brgds

Robert Gompper

Accepted Solutions (0)

Answers (1)

Answers (1)

RoGo
Explorer
0 Kudos

Dear hshegde,

i got the following information from Mr Pitz and it worked (see thread https://answers.sap.com/questions/13118220/sap-ewm-pmr.html)

<<<

All I got is a production scheduling profile with "WM Request" set to 2 - "Transfer Reqmt, Transfer Order, and Delivery Upon Rel" (where the last part is the important piece).

>>>

Set your WM Request to 2 in the corresponding "production scheduling profile" (material master).

P.S. Sorry for inverting some letters in your name in my first post.

Brgds