CK86_99 Multi level Costing BOM taking into account Scaled Pricing from PIR ?

0 Kudos

All,

I can run CK86_99 Multilevel BOM costing but is there any way for the costs to reflect the scaled pricing of the components from the PIR record?

So for example in CK86_99 I can choose a QTY that will not work on Material Master prices of my components but reflect the scaled prices maintained in the PIR?

Any help appreciated

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Have a look at OSS note 177006 and see whether you can carry out modifications to suit your requirement