Skip to Content

Change BOM

Hello SAP Commuinty,

new products are introduced into factory (A), the products BOM was copied and pasted from the other factory (B).

A process that we have introduced in the original factory (B) has not yet been introduced in factory A, Therefore, the BOM that was changed some time ago in the original factory ( I don't know when ) and now has been copied to the new factory. The BOM in the new factory is wrong.

Questions:

1) Can I change all products together?

2) What is the easiest way to change the BOM for a group of products, I find it really impractical to change product by product?

BTW: am brand new to SAP

Best Regards

Kareem

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Jul 11, 2020 at 07:20 PM

    Assuming both are on separate systems, You have to design and develop an automated interface to sync the BOM between the source to destination.

    The design should consider when the BOM in the destination system can be changed. If there are open orders SAP may or may not allow.

    Do some reading on BOM in SAP so you can come up with a design.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.