Hi everybody,
1. Plant has 3 slocs: A, B, C.
2. For material X i've maintained MRP* views for sloc A, also sloc A is excluded from MRP in MRP4 view.
3. Created PO with 3 lines: material X and sloc A, B and C.
The issue is that PO lines with sloc B and C appeared in MD04 as requirements when i expect them not to because there's no MRP* views maintained for B and C slocs at all.