Hello Experts,

I have a scenario - I have 2 resources (RES1 & RES2) which uses for the same purpose but the run rate is different. Second resource takes less time compare to the first resource. Appreciate if you can help me on below queries.

1. Main challenge - Both the resources shouldn't stop at the same time for cleaning (setup) activity. In the DS board,Setup time shouldn't be scheduled at the same time for both the resources. i mean, either one should be in working during other machine idle for setup/cleaning activity. How do we setup this relationship.

2. Run rate setup - I am trying to define RES1 & RES2 as alternative mode but the challenge is, In PDS, the run rate for RES1 & RES2 shows the same and unable to edit it. do we have any other solution instead of creating alternative PDS?

Thank you.

Add a comment
10|10000 characters needed characters exceeded

Related questions

0 Answers

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.