Hi SAP BW Guru's
There are two process chains which used to run on daily basis at a specific time in SAP BW production system .These two chains are suddenly stopped executing on its own without any reason .
I tried rescheduling these chains and activated and scheduled to run the usual timings on which is used to run...but its not running . When clicking on "Display All jobs " the relevant job is appearing in "Active " state from long time . As of now I am using "Executing Process chain Synchronously " as a temporary solution to run the chain .
I approached basis and shown them the job i have rescheduled they are saying it looks good i did not miss anything to give over there and it will start executing but in reality its not getting executed on its own.
Please your help in resolving these issues .