Hello, we use production planning in a repetitive manufacturing environment. We often run the same SKU for many days in a row. However, all dependent demand materials are shown as being required at the start of the production order. I see two options:
1. Split the order into daily buckets (one order of 5 days becomes five orders of 1 day). This is tedious based on the number of plants and production lines managed, and does not fix the problem with planned orders further in the future. Can SAP automate this process?
2. Can SAP calculate daily requirements for dependent demand components against one long production order?
Here you can see SKU 718347 running for 3 days (144,900 units):

And here you can see a "lump" of demand for a dependent component. You will also notice that the planner has manually overridden recommendations to stagger deliveries from the supplier. This volume equates to four full trailers of materials, delivering one every day. I wish to find a way for SAP to do this automatically: