Hello Gurus,
the Project was set up to collect off-booking cost for the equipments. The new range of WBS elements were set up at start of the year. They were set up to use prime rates only I.e
Plan costing va. - Prime rates
Act. Costing va. - Prime rates
Plan cost calc. - Determine plan cost
Despite the above setting the hours being booked are coming through at Prime rate and overheads rate.
How can sort this issue? Please help.
Thanks.