SNP planned order in past

How to disable it? What settings are responsible for this?

Also /SAPAPO/IF_EX_SNP_TRANS_SCHED implemented but method GET_DATE_CHECK_RULES has not changed

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jun 29 at 07:57 AM

    Hello,

    By implementing the BAdI /SAPAPO/SNP_TRANS_SCHED method GET_DATE_CHECK_RULES you can change this standard behaviour and define that the start dates of manually created/changed SNP stock transfer orders must not be in the past.

    It's for a stock transfer order not for SNP planned order.

    For SNP planned orders implement the BAdI /SAPAPO/SNP_PROD_SCHED method GET_DATE_CHECK_RULES and change the standard behaviour and define that the start dates of SNP orders are allowed be in the past in variable CV_MESSAGE_START_IN_PAST.

    Then you can have an error message /SAPAPO/SNP046 - Start date for production of product & is in the past.

    Please refer SAP note - 2424694 - User exit for the scheduling of SNP planned orders

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.