Hello All,
We have scenario like
2 plants 1000 and 1010 for this plant supplying plant is 1090
We have maintained Customer independent requirements in both plants using tcode - MD81.
Now when I run the MRP for both Plant 1000 and 1010. STO PR's getting generated in both plants 1000 and 1010 because of special procurement - 40 maintained in Material master.
Based on the stock availability in plant 1090 PR's getting created.
But Single PR's which is generated we required PR's based on the customer requirement. i.e One PR's for Plant 1000 and Plant 1010.
Please find the attached screenshot for reference
Kindly help..
Thanks and Regards
Jithendra