Discrepency in the scheduling CM25

103 Views

Hi Experts,

Can anyone please explain why there is a discrepancy in the operating time of the work center in recipe view to the detailed scheduling view in planned order in CM25 screen.

Even though the planned order is having the same base qty as the phase 0201 for work center R_C652 the duration in planned order is 24 + 19 hours where as in recipe view it is 21:830 hours .

Since CM25 does not consider GR processing time and floats and only looks into work center capacity the system should calculate scheduling to the same time of 21:830 hours shown in phase 0201.