Hello,
I have a scenario where a product can be procured from two vendors. I am using Transportation Cost Rate KF to set vendor priority (Product/Location/Ship To Location). No other cost setting has been set. The setting for Transportation Cost Rate in the first period is taken and used for the entire planning horizon. I am trying to time phase this where after a certain period, I want to switch the priority. Anything else that I may be missing? The only documentation I have found related using priority for source determination is link.
If any of you have tried time phasing of source determination using priority (transportation cost rate), please let me know what I am missing.
Thanks,
Krish