Longer time estimated for a production order

Hello SAP experts,

I have a situation where a single part number (sfg) was planned for manufacturing in a routing that comprised several work centers in its structure, but the output of time line was literally the sum of all work centers required capacities in hours to process that order, it was like the batch order had to pass from 1 work center to another without any parallel work between work centers, which ended up in several days needed to manufacture that order... it resulted way too much time estimated for that order. Any idea how this error can be fixed ?

Thank you!

Albert

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Jun 24, 2020 at 04:43 PM

    Hi ,

    Thanks! I'm new with SAP but I already identified the main cause at the operation routing due to wrong chosen settings in overlapping . It was solved by picking continous flow option.Thanks a lot for answering to my request. Have a good day! Albert

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 22, 2020 at 06:33 AM

    Hi,

    Can you share the screenshot of the production structure and process steps performed?

    Where are you creating production order ECC or S/4HANA?

    Best Regards,

    Lingaiah

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.