Jun 19, 2020 at 06:47 PM

Issue with Backward Scheduling- MRP producing days in History

173 Views

Hi Gurus,

While performing Backward Scheduling on FERT(with 3 level BOM), system is throwing dates in the past.

My setting:

OPPQ - Start date in past --> not checked

OPPR - Start date in past --> not checked

OPU5 - Backward Scheduling

Planning Strategy- 10; Procurement Type-E; In-house Production Time- 1 day and GR time - 1 day

My scenario:

My requirement date is 20.06.2020(Current day for me) with Qty 1000000 Ltr. (PIR)

I want system to perform Forward Scheduling as system should not go beyond current day and generate receipts in past

.

System has taken 8 days backward as capacity was not available, yet my expectations from System are to Forward Schedule this planned order instead of backward scheduling in past. I want to keep backward scheduling as standard.

Can Some one help me solve this issue.

Regards

Ajit