Hello
The requirement is as below.
MRO/Spare parts for preventive/breakdown maintenance are planned via Min-Max MRP and procured from vendors. These materials are common across plants. However each plant procures independently, this leads to excess inventory org.wide. So there is a requirement to first request internal stock transfer before procuring externally for managing inventory levels better.
Let me paint a scenario
Component #123 | Receiving Plant : AAA1
Regular vendor for component #123 at plant AAA1 is VENDOR1
Component #123 stock also present in plants BBB1, CCC1, DDD1
BBB1 = 30 EA
CCC1 = 40 EA
DDD1 = 30 EA
Now, Say there is a requirement for 150 for component #123 in plant AAA1
The expectation is MRP should create the following requirement elements,
Stock transfer requisition for 30 EA with supplying plant BBB1
Stock transfer requisition for 40 EA with supplyin plant CCC1
Stock transfer requisition for 30 EA with supplying plant DDD1
External Purchase requisition for 50 EA with vendor VENDOR1
To my knowledge, this is not possible via standard set up. Is there a BADI that can help achieve this requirement?