TS Finite Heuristic - Static Period of supply

186 Views

I am trying to model build ahead (end item) using the static period of supply seems to be the only option available in Finite Heuristic to model Safety Days like behavior. I have set the Lot Sizing Procedure to 1 in Product Location and updated the SubPeriodsofSupply KF to 2.

Expected Result: demand from the 2 periods in the future to be pulled into the current period.

Actual Result: demand from the subsequent (1) period is pulled into the current period and not 2 periods as expected

(Link to SAP Help on Static Periods of Supply)

Lead Times Modeled: Production Lead Time is 1 week, Transportation Lead Time for components is 1 week

Am I missing any other MD setting?

Any help would be much appreciated.

Thanks,
Krish