SAP PM Workorder- Allow PO updates after TECO

1201 Views

Hi Experts,

Based on current business process at my company, PM work order is executed using stock available in the "truck/mobile van" which was previously issued from store. The "truck/mobile van" stock is then replenished at a later date using either the reservation/PO from the work order. In many cases, the PO needs to be updated after the work order is TECOed. Since SAP doesn't allow PO updates if work order is TECO, the work order needs to be UnTECO and TECO at a later date, thus messing up the completion dates.

I explored the option of allowing RMBE (Material purchase order) for TECO in BS22. This, however, is not suggested as it affects all SAP objects with status and cannot be restricted.

Has anyone worked on allowing business transactions using custom development? Any other ideas on how this can be achieved?

Regards,

Jibitesh