SAP PM - You must specify a batch for material XXXXXXXX Message No. IW870

282 Views

Hi,

when I try to schedule a Maintenance Plan with IP10 I receive this information message:

There is no option of filling split valuation value/the field "Batch" in general tasklist via IA05.

Now the problem is if I schedule maintenance plan via IP30 deadline monitoring with task list having split valuated component assigned in it, although the plan gets schedule but call object "Order" doesn't gets created which is because of this information message which I am getting via IP10.

I have also tried assigning/changing/deleting the message IW870 with different message category - blank/error/warning but its not sorting out the issue.

If any solution to overcome this issue. Please suggest. Is it a SAP bug ?

Thanks

Nimish