Skip to Content
0
Jun 12, 2020 at 08:04 AM

TRLT- Total replenishment lead time for special procurement type materials not calculated

845 Views

Hi Experts,

The FERT materials having in MRP views Procurement type X, Special procurement key 41, Availability check 02, Tot. repl. lead time 60 days. While creating a Sales Order if the Availability situation cannot meet the requested delivery date, the system goes to Availability screen automatically with out considering TRLT- Total replenishment lead time.

The FERT materials having in MRP views Procurement type X, Availability check 02, Tot. repl. lead time 60 days. While creating a Sales Order if the Availability situation were meet the requested delivery date, the system goes to Availability screen automatically with considering TRLT- Total replenishment lead time.

Why does system not considered TRLT- Total replenishment lead time for special procurement type flagged materials?