Hi Experts,
The FERT materials having in MRP views Procurement type X, Special procurement key 41, Availability check 02, Tot. repl. lead time 60 days. While creating a Sales Order if the Availability situation cannot meet the requested delivery date, the system goes to Availability screen automatically with out considering TRLT- Total replenishment lead time.
The FERT materials having in MRP views Procurement type X, Availability check 02, Tot. repl. lead time 60 days. While creating a Sales Order if the Availability situation were meet the requested delivery date, the system goes to Availability screen automatically with considering TRLT- Total replenishment lead time.
Why does system not considered TRLT- Total replenishment lead time for special procurement type flagged materials?