MRP proposes planned order requirements before firmed planned orders, is there a method or config that prevents this happening?
I am aware that a planning time fence may help but I do not want to implement this as a static figure against products, we have some capacity restraints that require us to plan using CM25 that firms the planned orders based on the capacity, mrp runs and drops planned orders in front of the already planned firmed ones.