Dear all,
I would like to create a dependency rule to be assigned at a operation in a super routing that is able to test the availability of a specific component in the BOM.
We are speaking about a configurable material to be produced (MTO of course) and for such reason a component can be added manually to the corresponding order BOM without a characteristic to evaluate. In this case I would like to have a special operation to be determinated during PP order creation only if that component is available in the same PP order.
Is there a possibility without using user-exit or further characteristics?
Thanks
Bye
Gabriele